West Drewry Lane Stormwater Improvements

Culvert Replacement / Streambank Stabilization

We improved the stormwater system on West Drewry Lane. The 72-inch metal pipe was replaced with a reinforced concrete box culvert. We also upgraded the water and sewer systems.

We finished this project in 2018. There are a few repairs that need to be made to the stream. More details below. 

Project Details

 
Type:
Stormwater
Budget:
$1 - $2 million (initial project) $100,000 (repairs)
Project Lead:
Stormwater Management
Contractors:
Initial Project: Arcadis U.S., Inc. (Engineer Consultant), Browe Construction Company (Contractor) Repairs: In-house

Contact

 

David Kiker, PE
Project Manager
919-996-4074

Lead Department:
Engineering Services
Participating Department:
Water
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete.

Phase Contacts

 

Veronica High, PE
Stormwater Administrator
919-996-4018

Lead Department:
Engineering Services

Design

This phase is complete.

Phase Contacts

 

Veronica High, PE
Stormwater Administrator
919-996-4018

Lead Department:
Engineering Services

Construction

This phase is complete.

Phase Contacts

 

Veronica High, PE
Stormwater Administrator
919-996-4018

Lead Department:
Engineering Services

Complete

Repairs Required

Since we’ve finished the project in 2018, there have been some issues with the stream on W. Drewry Lane. The streambanks are unstable and in some areas have completely failed. We are planning to repair the stream by:

  • Resetting some of the boulders in the stream;
  • Reshaping the stream; and,
  • Adding 30 feet to the boulder wall at the culvert outlet that carries stormwater under W. Drewry Lane.

Recent Work

We finished the design for these repairs. We also received all environmental permits in July 2021. We're planning to start construction in early 2022. More details coming soon.  

Phase Contacts

 

David Kiker, PE
Project Manager
919-996-4074

Lead Department:
Engineering Services

Schedule

Date Activity
Summer 2017 Project design complete
Spring 2017 - Summer 2018 Project construction phase complete
Late Fall 2020 - Winter 2021 Repairs identified; Design completed; Preparing for construction phase
Spring 2021 Construction bid process
Early Winter 2022 Construction for repairs begins

Initial Construction Work

The contractor, Browe Construction Company, finished construction in 2018. This included: 

  • Installing a six-foot-by-seven-foot box culvert; 
  • Finishing the streambank stabilization part of the project, which included grading the streambanks and installing structures that reduce erosion and control the flow of the stream; 
  • Installing a sewer manhole and replaced sections of sewer and water pipes in the project area; and, 
  • Replacing the curb and gutter and repaving the road. 

The warranty period ended in July 2019.

History

A large rainstorm in September 2012 bent and eroded a metal stormwater pipe on West Drewry Lane. The area around the pipe was unsafe, so we closed the road for emergency repairs in 2013. This project made more upgrades to the system.